Now Under Construction
Parliament & Co
Commercial
Amenities
New Corktown
Retail
Event Space
Live/Work
Team
Construction Update
Register
Portal Access
Now Under Construction
Parliament&Co
/
Commercial
/
Amenities
/
New Corktown
/
Retail
/
Event Space
/
Live-Work
/
Team
Construction Update
Register
Now Under Construction
Construction Update
Select an image below to view the construction progress at Parliamnet & Co.
March 28, 2023
March 21, 2023
March 15, 2023
March 14, 2023
March 7, 2023
March 6, 2023
March 2, 2023
March 1, 2023
February 28, 2023
February 17, 2023
February 14, 2023
February 13, 2023
February 8, 2023
February 1, 2023
January 26, 2023
January 25, 2023
January 24, 2023
January 23, 2023
January 18, 2023
January 16, 2023
January 11, 2023
December 7, 2022
December 2, 2022
November 24, 2022
October 14, 2022
September 23, 2022
September 16, 2022
September 2, 2022
August 31st, 2022
August 29th, 2022
August 10th, 2022
July 11th, 2022
June 27th, 2022
May 5th, 2022
April 29th, 2022
March 10th, 2022
February 3rd, 2022
September 7th, 2021
August 27th, 2021
August 9th, 2021
July 28th, 2021
July 20th, 2021
x
| Construction Update - July 7, 2021
x
| Construction Update - July 7, 2021
x
| Construction Update - July 7, 2021
x
| Construction Update - July 8, 2021
x
| Construction Update - July 8, 2021
x
| Construction Update - July 8, 2021
x
| Construction Update - July 12, 2021
x
| Construction Update - July 12, 2021
x
| Construction Update - July 12, 2021
x
| Construction Update - July 13, 2021
x
| Construction Update - July 13, 2021
x
| Construction Update - July 13, 2021
x
| Construction Update - July 20, 2021
x
| Construction Update - July 20, 2021
x
| Construction Update - July 20, 2021
x
| Construction Update - July 21, 2021
x
| Construction Update - July 21, 2021
x
| Construction Update - July 21, 2021
x
| Construction Update - July 23, 2021
x
| Construction Update - July 23, 2021
x
| Construction Update - July 23, 2021
x
| Construction Update - July 26, 2021
x
| Construction Update - July 26, 2021
x
| Construction Update - July 26, 2021
x
| Construction Update - July 28, 2021
x
| Construction Update - July 28, 2021
x
| Construction Update - July 28, 2021
x
| Construction Update - July 30, 2021
x
| Construction Update - July 30, 2021
x
| Construction Update - July 30, 2021
x
| Construction Update - August 4, 2021
x
| Construction Update - August 4, 2021
x
| Construction Update - August 4, 2021
x
| Construction Update - August 6, 2021
x
| Construction Update - August 6, 2021
x
| Construction Update - August 6, 2021
x
| Construction Update - August 9, 2021
x
| Construction Update - August 9, 2021
x
| Construction Update - August 9, 2021
x
| Construction Update - August 11, 2021
x
| Construction Update - August 11, 2021
x
| Construction Update - August 11, 2021
x
| Construction Update - August 13, 2021
x
| Construction Update - August 13, 2021
x
| Construction Update - August 13, 2021
x
| Construction Update - August 24, 2021
x
| Construction Update - August 24, 2021
x
| Construction Update - August 24, 2021
x
| Construction Update - August 27, 2021
x
| Construction Update - August 27, 2021
x
| Construction Update - August 27, 2021
x
| Construction Update - August 31, 2021
x
| Construction Update - August 31, 2021
x
| Construction Update - August 31, 2021
x
| Construction Update - September 2, 2021
x
| Construction Update - September 2, 2021
x
| Construction Update - September 2, 2021
x
| Construction Update - September 7, 2021
x
| Construction Update - September 7, 2021
x
| Construction Update - September 7, 2021
x
| Construction Update - September 13, 2021
x
| Construction Update - September 13, 2021
x
| Construction Update - September 13, 2021
x
| Shoring Has Started - February 1, 2022
x
| Shoring Has Started - February 1, 2022
x
| Shoring Has Started - February 1, 2022
x
| Shoring Continues - February 10, 2022
x
| Shoring Continues - February 10, 2022
x
| Shoring Continues - February 10, 2022
x
| Shoring Continues - February 18, 2022
x
| Shoring Continues - February 18, 2022
x
| Shoring Continues - February 18, 2022
x
| Shoring Continues - February 24, 2022
x
| Shoring Continues - February 24, 2022
x
| Shoring Continues - February 24, 2022
x
| Shoring Work Continues - March 2, 2022
x
| Shoring Work Continues - March 2, 2022
x
| Shoring Work Continues - March 2, 2022
x
| Shoring Work Continues - March 10, 2022
x
| Shoring Work Continues - March 10, 2022
x
| Shoring Work Continues - March 10, 2022
x
| Shoring Work Continues - March 16, 2022
x
| Shoring Work Continues - March 16, 2022
x
| Shoring Work Continues - March 16, 2022
x
| Shoring Work Continues - March 21, 2022
x
| Shoring Work Continues - March 21, 2022
x
| Shoring Work Continues - March 21, 2022
x
| Shoring Work Continues - April 4, 2022
x
| Shoring Work Continues - April 4, 2022
x
| Shoring Work Continues - April 4, 2022
x
| Shoring Work Continues - April 18, 2022
x
| Shoring Work Continues - April 18, 2022
x
| Shoring Work Continues - April 18, 2022
x
| Shoring Work Continues - April 29, 2022
x
| Shoring Work Continues - April 29, 2022
x
| Shoring Work Continues - April 29, 2022
x
| Shoring Work Continues - May 5, 2022
x
| Shoring Work Continues - May 5, 2022
x
| Shoring Work Continues - May 5, 2022
x
| May 16, 2022
x
| May 16, 2022
x
| May 16, 2022
x
| June 27, 2022
x
| June 27, 2022
x
| June 27, 2022
x
| July 6, 2022
x
| July 6, 2022
x
| July 6, 2022
x
| July 8, 2022
x
| July 8, 2022
x
| July 8, 2022
x
| July 11, 2022
x
| July 11, 2022
x
| July 11, 2022
x
| July 19, 2022
x
| July 19, 2022
x
| July 19, 2022
x
| August 10, 2022 – Excavation Continues
x
| August 10, 2022 – Shaving of King and Filler Piles
x
| August 10, 2022 – Lagging Work Along the West Side of the Property
x
| August 29, 2022 – Crane Pad Completed
x
| August 29, 2022 – Crane Pad Completed
x
| August 29, 2022 – Crane Pad Completed
x
| August 31, 2022 – CRANE IS ERECTED
x
| August 31, 2022 – CRANE IS ERECTED
x
| August 31, 2022 – CRANE IS ERECTED
x
| September 2, 2022 – Finishing off the Walers and Lagging Work
x
| September 2, 2022 – Finishing off the Walers and Lagging Work
x
| September 2, 2022 – Finishing off the Walers and Lagging Work
x
| September 16, 2022 – Water Proofing and Footing Formation Continues
x
| September 16, 2022 – Water Proofing and Footing Formation Continues
x
| September 16, 2022 – Water Proofing and Footing Formation Continues
x
| September 23, 2022 – Detailed Excavation and Preparation for Concrete Forming
x
| September 23, 2022 – View Looking East Showing Detailed Excavation and Blindside Waterproofing
x
| September 23, 2022 – Crane on Site
x
| October 14, 2022 – Verticals completed and cross braces boxed out
x
| October 14, 2022 – Verticals being formed and precast sump pits are placed
x
| October 14, 2022 – Aerial view showing verticals completed and rebar columns ready for forms
x
| November 24, 2022 – Slab On Grade 50% Complete
x
| November 24, 2022 – Slab On Grade 50% Complete
x
| November 24, 2022 – Slab On Grade 50% Complete
x
| December 2, 2022 – Table Forms in place for P1 structural slab.
Back fill of the southwest side under the Colonnade.
x
| December 2, 2022 – View looking East from Slab On Grade.
x
| December 2, 2022 – Aerial view capturing preparation for balance of SOG and Table Forms for P1 structural slab.
x
| December 2, 2022 – Table Forms in place for P1 structural slab.
Back fill of the southwest side under the Colonnade.
x
| December 2, 2022 – View looking East from Slab On Grade
x
| December 2, 2022 – Aerial view capturing preparation for balance of SOG and Table Forms for P1 structural slab
x
| December 2, 2022 – Table Forms in place for P1 structural slab
Back fill of the southwest side under the Colonnade.
x
| December 2, 2022 – View looking East from Slab On Grade
x
| December 2, 2022 – Aerial view capturing preparation for balance of SOG and Table Forms for P1 structural slab
x
| December 7, 2022 – Rebar placement underway for P1 structural slab
x
| December 7, 2022 – Rebar placement on table forms for P1, eastern section
x
| December 7, 2022 – Balance of Slab On Grade now 100% complete
x
| January 11, 2023 – Waterproofing has started from P1 to grade
x
| January 11, 2023 – Cross braces P2 to P1 being cut
x
| January 11, 2023 – Ramp from P1 to P2 complete
x
| January 11, 2023 – Aerial drone image
x
| January 11, 2023 – Waterproofing from P1 to ground underway
x
| January 11, 2023 – Verticals from P1 to ground underway
x
| January 16, 2023 – Verticals for P1 to grade looking west
x
| January 16, 2023 – Pile chipping on the north side started
x
| January 16, 2023 – Rebar placement for south side perimeter wall after waterproofing
x
| January 18, 2023 – Form work continues to grade
x
| January 18, 2023 – Perimeter rebar work continues to grade on the south side
x
| January 18, 2023 – Forming stairwell on the southeast side of the property
x
| January 23, 2023 – Shotcrete on the west perimeter wall on P1 to grade started
x
| January 23, 2023 – Shotcrete on the west perimeter wall on P1 to grade started
x
| January 23, 2023 – Shotcrete on the west perimeter wall on P1 to grade started
x
| January 24, 2023 – Pile chipping on the north side continues for the ground floor slab
x
| January 24, 2023 – Waterprofing completed and rebar placement on the south parimeter wall started
x
| January 24, 2023 – Waterprofing completed and rebar placement on the west parimeter wall started
x
| January 25, 2023 – Placing rebar for garage ramp wall P1 to grade
x
| January 25, 2023 – Installing inside form box for elevator, to receive rebar
x
| January 25, 2023 – Placing rebar for garage ramp wall P1 to grade
x
| January 26, 2023 – Shotcrete complete on west wall, P1 to grade
x
| January 26, 2023 – Aerial view looking southwest showing verticals, P1 to grade
x
| January 26, 2023 – Rebar in place on south perimeter wall and ramp wall, P1 to grade
x
| February 1, 2023 – Forming elevator shaft, from P1 to grade
x
| February 1, 2023 – South perimeter wall formed and stripped, from P1 to grade
x
| February 1, 2023 – Rebar placed in front of waterproofing on the east perimeter wall, from P1 to grade
x
| February 13, 2023 – Rebar placement started in front of waterproofing on the north side
x
| February 13, 2023 – Rebar placement on the south side perimeter wall continues
x
| February 13, 2023 – Below grade piping for drains has started
x
| February 14, 2023 – In preparation for slab on grade required rebar is on site
x
| February 14, 2023 – Overall view looking west showing current site condition
x
| February 14, 2023 – Tables for ground floor slab and beams below
x
| February 17, 2023 – Tables for ground floor slab and beams below
x
| February 17, 2023 – Shotcrete completed on south wall P1 to grade. Rebar visible for ramp, from ground to P1
x
| February 17, 2023 – Tables and rebar shown for the Storm Water Tank base located at the south west corner
x
| February 28, 2023 – Building forms for ground floor structural slab
x
| February 28, 2023 – View looking west showing site progress
x
| February 28, 2023 – Preparation underway for buildout of ramp from Ground to P1
x
| March 1, 2023 – Deck for ramp from P1 to Ground level well underway
x
| March 1, 2023 – Perimeter wall P1 to Ground level on east side now complete
x
| March 1, 2023 – Storm water tank floor complete
x
| March 2, 2023 – Image looking northeast showing the ramp
x
| March 2, 2023 – View looking east showing the perimeter wall on the east side completed, from P1 to Ground
x
| March 2, 2023 – Rebar placement for transfer beams related to Ground floor slab underway
x
| March 6, 2023 – Rebar placement for ramp, Ground to P1 70% complete
x
| March 6, 2023 – Additional section for the ramp from Ground to P1 shown on the southeast corner
x
| March 6, 2023 – Preparation for waterproofing has begun on the northwest side
x
| March 7, 2023 – Rebar placement for Ground floor slab continues
x
| March 7, 2023 – View of rebar on ramp from P1 to Ground
x
| March 7, 2023 – Pipes and drains being installed below grade
x
| March 9, 2023 – P1 to Ground ramp first pour complete
x
| March 9, 2023 – In preparation of grade beam at the northwest corner
x
| March 9, 2023 – Rebar placement for ground floor slab continues
x
| March 14, 2023 – Conduits now being installed for Pour 1 of Ground floor slab
x
| March 14, 2023 – Forms are being extended for Pour 2 of the ramp towards the eastern corner, from P1 to Ground
x
| March 14, 2023 – Precast stairs now being installed below grade
x
| March 15, 2023 – Wall forms being placed for storm water tank
x
| March 15, 2023 – Additional conduit being installed for Ground floor slab, pour 1
x
| March 15, 2023 – Northwest side showing waterproofing and nelson studs in preparation for grade beam
x
| March 21, 2023 – Forms for ramp continue from the east corner heading north
x
| March 21, 2023 – Forms for ramp continue from the east corner heading north
x
| March 21, 2023 – Forms for ramp continue from the east corner heading north
x
| March 28, 2023 – Rebar added for second pour of Ramp Section
x
| March 28, 2023 – Conduits added to a pour for Ground Floor Slab
x
| March 28, 2023 – Rebar placed for Grade Beam pour 1 Ground Floor Slab