Select an image below to view the construction progress at Parliamnet & Co.
September 6, 2024
August 29, 2024
July 31, 2024
June 26, 2024
June 15, 2024
June 5, 2024
June 4, 2024
March 18, 2024
March 8, 2024
January 30, 2024
December 6, 2023
November 27, 2023
Currently Forming Level 8
November 13, 2023
October 11, 2023
Aerial view of the perimeter for Parliament & Co.
October 11, 2023
September 29, 2023
September 27, 2023
Parliament & Co. Aerial view of the West perimeter
Parliament & Co. Aerial view of the East perimeter
September 27, 2023
September 26, 2023
September 20, 2023
August 30, 2023
August 14, 2023
August 2, 2023
July 21, 2023
July 14, 2023
July 7, 2023
June 29, 2023
June 13, 2023
June 7, 2023
Parliament & Co. East Section 360° Video
Parliament & Co. Aerial Video
May 25, 2023
May 16, 2023
April 17, 2023
April 12, 2023
April 4, 2023
March 31, 2023
March 30, 2023
Aerial view of the perimeter for Warehouse Lofts Toronto
March 28, 2023
March 21, 2023
March 15, 2023
March 14, 2023
March 7, 2023
March 6, 2023
March 2, 2023
March 1, 2023
February 28, 2023
February 17, 2023
February 14, 2023
February 13, 2023
February 8, 2023
February 1, 2023
January 26, 2023
January 25, 2023
January 24, 2023
January 23, 2023
January 18, 2023
January 16, 2023
January 11, 2023
December 7, 2022
December 2, 2022
November 24, 2022
October 14, 2022
September 23, 2022
September 16, 2022
September 2, 2022
August 31st, 2022
August 29th, 2022
August 10th, 2022
July 11th, 2022
June 27th, 2022
May 5th, 2022
April 29th, 2022
March 10th, 2022
February 3rd, 2022
September 7th, 2021
August 27th, 2021
August 9th, 2021
July 28th, 2021
July 20th, 2021
x | Construction Update - July 7, 2021
x | Construction Update - July 7, 2021
x | Construction Update - July 7, 2021
x | Construction Update - July 8, 2021
x | Construction Update - July 8, 2021
x | Construction Update - July 8, 2021
x | Construction Update - July 12, 2021
x | Construction Update - July 12, 2021
x | Construction Update - July 12, 2021
x | Construction Update - July 13, 2021
x | Construction Update - July 13, 2021
x | Construction Update - July 13, 2021
x | Construction Update - July 20, 2021
x | Construction Update - July 20, 2021
x | Construction Update - July 20, 2021
x | Construction Update - July 21, 2021
x | Construction Update - July 21, 2021
x | Construction Update - July 21, 2021
x | Construction Update - July 23, 2021
x | Construction Update - July 23, 2021
x | Construction Update - July 23, 2021
x | Construction Update - July 26, 2021
x | Construction Update - July 26, 2021
x | Construction Update - July 26, 2021
x | Construction Update - July 28, 2021
x | Construction Update - July 28, 2021
x | Construction Update - July 28, 2021
x | Construction Update - July 30, 2021
x | Construction Update - July 30, 2021
x | Construction Update - July 30, 2021
x | Construction Update - August 4, 2021
x | Construction Update - August 4, 2021
x | Construction Update - August 4, 2021
x | Construction Update - August 6, 2021
x | Construction Update - August 6, 2021
x | Construction Update - August 6, 2021
x | Construction Update - August 9, 2021
x | Construction Update - August 9, 2021
x | Construction Update - August 9, 2021
x | Construction Update - August 11, 2021
x | Construction Update - August 11, 2021
x | Construction Update - August 11, 2021
x | Construction Update - August 13, 2021
x | Construction Update - August 13, 2021
x | Construction Update - August 13, 2021
x | Construction Update - August 24, 2021
x | Construction Update - August 24, 2021
x | Construction Update - August 24, 2021
x | Construction Update - August 27, 2021
x | Construction Update - August 27, 2021
x | Construction Update - August 27, 2021
x | Construction Update - August 31, 2021
x | Construction Update - August 31, 2021
x | Construction Update - August 31, 2021
x | Construction Update - September 2, 2021
x | Construction Update - September 2, 2021
x | Construction Update - September 2, 2021
x | Construction Update - September 7, 2021
x | Construction Update - September 7, 2021
x | Construction Update - September 7, 2021
x | Construction Update - September 13, 2021
x | Construction Update - September 13, 2021
x | Construction Update - September 13, 2021
x | Shoring Has Started - February 1, 2022
x | Shoring Has Started - February 1, 2022
x | Shoring Has Started - February 1, 2022
x | Shoring Continues - February 10, 2022
x | Shoring Continues - February 10, 2022
x | Shoring Continues - February 10, 2022
x | Shoring Continues - February 18, 2022
x | Shoring Continues - February 18, 2022
x | Shoring Continues - February 18, 2022
x | Shoring Continues - February 24, 2022
x | Shoring Continues - February 24, 2022
x | Shoring Continues - February 24, 2022
x | Shoring Work Continues - March 2, 2022
x | Shoring Work Continues - March 2, 2022
x | Shoring Work Continues - March 2, 2022
x | Shoring Work Continues - March 10, 2022
x | Shoring Work Continues - March 10, 2022
x | Shoring Work Continues - March 10, 2022
x | Shoring Work Continues - March 16, 2022
x | Shoring Work Continues - March 16, 2022
x | Shoring Work Continues - March 16, 2022
x | Shoring Work Continues - March 21, 2022
x | Shoring Work Continues - March 21, 2022
x | Shoring Work Continues - March 21, 2022
x | Shoring Work Continues - April 4, 2022
x | Shoring Work Continues - April 4, 2022
x | Shoring Work Continues - April 4, 2022
x | Shoring Work Continues - April 18, 2022
x | Shoring Work Continues - April 18, 2022
x | Shoring Work Continues - April 18, 2022
x | Shoring Work Continues - April 29, 2022
x | Shoring Work Continues - April 29, 2022
x | Shoring Work Continues - April 29, 2022
x | Shoring Work Continues - May 5, 2022
x | Shoring Work Continues - May 5, 2022
x | Shoring Work Continues - May 5, 2022
x | May 16, 2022
x | May 16, 2022
x | May 16, 2022
x | June 27, 2022
x | June 27, 2022
x | June 27, 2022
x | July 6, 2022
x | July 6, 2022
x | July 6, 2022
x | July 8, 2022
x | July 8, 2022
x | July 8, 2022
x | July 11, 2022
x | July 11, 2022
x | July 11, 2022
x | July 19, 2022
x | July 19, 2022
x | July 19, 2022
x | August 10, 2022 – Excavation Continues
x | August 10, 2022 – Shaving of King and Filler Piles
x | August 10, 2022 – Lagging Work Along the West Side of the Property
x | August 29, 2022 – Crane Pad Completed
x | August 29, 2022 – Crane Pad Completed
x | August 29, 2022 – Crane Pad Completed
x | August 31, 2022 – CRANE IS ERECTED
x | August 31, 2022 – CRANE IS ERECTED
x | August 31, 2022 – CRANE IS ERECTED
x | September 2, 2022 – Finishing off the Walers and Lagging Work
x | September 2, 2022 – Finishing off the Walers and Lagging Work
x | September 2, 2022 – Finishing off the Walers and Lagging Work
x | September 16, 2022 – Water Proofing and Footing Formation Continues
x | September 16, 2022 – Water Proofing and Footing Formation Continues
x | September 16, 2022 – Water Proofing and Footing Formation Continues
x | September 23, 2022 – Detailed Excavation and Preparation for Concrete Forming
x | September 23, 2022 – View Looking East Showing Detailed Excavation and Blindside Waterproofing
x | September 23, 2022 – Crane on Site
x | October 14, 2022 – Verticals completed and cross braces boxed out
x | October 14, 2022 – Verticals being formed and precast sump pits are placed
x | October 14, 2022 – Aerial view showing verticals completed and rebar columns ready for forms
x | November 24, 2022 – Slab On Grade 50% Complete
x | November 24, 2022 – Slab On Grade 50% Complete
x | November 24, 2022 – Slab On Grade 50% Complete
x | December 2, 2022 – Table Forms in place for P1 structural slab.
Back fill of the southwest side under the Colonnade.
x | December 2, 2022 – View looking East from Slab On Grade.
x | December 2, 2022 – Aerial view capturing preparation for balance of SOG and Table Forms for P1 structural slab.
x | December 2, 2022 – Table Forms in place for P1 structural slab.
Back fill of the southwest side under the Colonnade.
x | December 2, 2022 – View looking East from Slab On Grade
x | December 2, 2022 – Aerial view capturing preparation for balance of SOG and Table Forms for P1 structural slab
x | December 2, 2022 – Table Forms in place for P1 structural slab
Back fill of the southwest side under the Colonnade.
x | December 2, 2022 – View looking East from Slab On Grade
x | December 2, 2022 – Aerial view capturing preparation for balance of SOG and Table Forms for P1 structural slab
x | December 7, 2022 – Rebar placement underway for P1 structural slab
x | December 7, 2022 – Rebar placement on table forms for P1, eastern section
x | December 7, 2022 – Balance of Slab On Grade now 100% complete
x | January 11, 2023 – Waterproofing has started from P1 to grade
x | January 11, 2023 – Cross braces P2 to P1 being cut
x | January 11, 2023 – Ramp from P1 to P2 complete
x | January 11, 2023 – Aerial drone image
x | January 11, 2023 – Waterproofing from P1 to ground underway
x | January 11, 2023 – Verticals from P1 to ground underway
x | January 16, 2023 – Verticals for P1 to grade looking west
x | January 16, 2023 – Pile chipping on the north side started
x | January 16, 2023 – Rebar placement for south side perimeter wall after waterproofing
x | January 18, 2023 – Form work continues to grade
x | January 18, 2023 – Perimeter rebar work continues to grade on the south side
x | January 18, 2023 – Forming stairwell on the southeast side of the property
x | January 23, 2023 – Shotcrete on the west perimeter wall on P1 to grade started
x | January 23, 2023 – Shotcrete on the west perimeter wall on P1 to grade started
x | January 23, 2023 – Shotcrete on the west perimeter wall on P1 to grade started
x | January 24, 2023 – Pile chipping on the north side continues for the ground floor slab
x | January 24, 2023 – Waterprofing completed and rebar placement on the south parimeter wall started
x | January 24, 2023 – Waterprofing completed and rebar placement on the west parimeter wall started
x | January 25, 2023 – Placing rebar for garage ramp wall P1 to grade
x | January 25, 2023 – Installing inside form box for elevator, to receive rebar
x | January 25, 2023 – Placing rebar for garage ramp wall P1 to grade
x | January 26, 2023 – Shotcrete complete on west wall, P1 to grade
x | January 26, 2023 – Aerial view looking southwest showing verticals, P1 to grade
x | January 26, 2023 – Rebar in place on south perimeter wall and ramp wall, P1 to grade
x | February 1, 2023 – Forming elevator shaft, from P1 to grade
x | February 1, 2023 – South perimeter wall formed and stripped, from P1 to grade
x | February 1, 2023 – Rebar placed in front of waterproofing on the east perimeter wall, from P1 to grade
x | February 8, 2023
x | February 8, 2023
x | February 8, 2023
x | February 13, 2023 – Rebar placement started in front of waterproofing on the north side
x | February 13, 2023 – Rebar placement on the south side perimeter wall continues
x | February 13, 2023 – Below grade piping for drains has started
x | February 14, 2023 – In preparation for slab on grade required rebar is on site
x | February 14, 2023 – Overall view looking west showing current site condition
x | February 14, 2023 – Tables for ground floor slab and beams below
x | February 17, 2023 – Tables for ground floor slab and beams below
x | February 17, 2023 – Shotcrete completed on south wall P1 to grade. Rebar visible for ramp, from ground to P1
x | February 17, 2023 – Tables and rebar shown for the Storm Water Tank base located at the south west corner
x | February 28, 2023 – Building forms for ground floor structural slab
x | February 28, 2023 – View looking west showing site progress
x | February 28, 2023 – Preparation underway for buildout of ramp from Ground to P1
x | March 1, 2023 – Deck for ramp from P1 to Ground level well underway
x | March 1, 2023 – Perimeter wall P1 to Ground level on east side now complete
x | March 1, 2023 – Storm water tank floor complete
x | March 2, 2023 – Image looking northeast showing the ramp
x | March 2, 2023 – View looking east showing the perimeter wall on the east side completed, from P1 to Ground
x | March 2, 2023 – Rebar placement for transfer beams related to Ground floor slab underway
x | March 6, 2023 – Rebar placement for ramp, Ground to P1 70% complete
x | March 6, 2023 – Additional section for the ramp from Ground to P1 shown on the southeast corner
x | March 6, 2023 – Preparation for waterproofing has begun on the northwest side
x | March 7, 2023 – Rebar placement for Ground floor slab continues
x | March 7, 2023 – View of rebar on ramp from P1 to Ground
x | March 7, 2023 – Pipes and drains being installed below grade
x | March 9, 2023 – P1 to Ground ramp first pour complete
x | March 9, 2023 – In preparation of grade beam at the northwest corner
x | March 9, 2023 – Rebar placement for ground floor slab continues
x | March 14, 2023 – Conduits now being installed for Pour 1 of Ground floor slab
x | March 14, 2023 – Forms are being extended for Pour 2 of the ramp towards the eastern corner, from P1 to Ground
x | March 14, 2023 – Precast stairs now being installed below grade
x | March 15, 2023 – Wall forms being placed for storm water tank
x | March 15, 2023 – Additional conduit being installed for Ground floor slab, pour 1
x | March 15, 2023 – Northwest side showing waterproofing and nelson studs in preparation for grade beam
x | March 21, 2023 – Forms for ramp continue from the east corner heading north
x | March 21, 2023 – Forms for ramp continue from the east corner heading north
x | March 21, 2023 – Forms for ramp continue from the east corner heading north
x | March 28, 2023 – Rebar added for second pour of Ramp Section
x | March 28, 2023 – Conduits added to a pour for Ground Floor Slab
x | March 28, 2023 – Rebar placed for Grade Beam pour 1 Ground Floor Slab
x | March 31, 2023 – Second pour for Ramp complete
x | March 31, 2023 – Preparation for balance of Grade Beam almost complete
x | March 31, 2023 – Concrete Matt for pour 1 of Ground Floor Slab complete
x | April 4, 2023 – Second pour of Ramp completed
x | April 4, 2023 – Northwest section, rebar for Grade Beam now in place
x | April 4, 2023 – Northeast side ready to receive waterproofing
x | April 12, 2023 – Grade Beam rebar placement for pour 2 completed
x | April 12, 2023 – Pour 3 Grade Beam waterproofing completed
x | April 12, 2023 – Waterproofing for Stormwater tank floor completed
x | April 17, 2023 – Additional Rebar now being placed for the final ramp section towards the entrance off Anne Hilliard Lane
x | April 17, 2023 – Verticals from Ground to Level 2 starting
x | April 17, 2023 – North side of Pour 1 Ground Floor Slab, reveals strip footing for future parameter wall from Ground to Level 2
x | May 16, 2023 – Verticals are being formed from Ground to Second Level
x | May 16, 2023 – Ground Floor Slab now complete
x | May 16, 2023 – Forming in place for the East Perimeter Wall, from Ground to Mezzanine Level
x | May 25, 2023 – Decking to Level 2 on the West Side along Parliament Street has started. Circular columns along the South Side have been poured.
x | May 25, 2023 – Ramp section to Ground Level completed for the vehicular entry at Anna Hilliard Lane
x | May 25, 2023 – Double Sided forms for the North Side Perimeter Wall in place
x | June 13, 2023 – Extent of Decking for Level 2 on the Southern Limit, next to the land conveyance
x | June 13, 2023 – Formwork for parking roundabout in place from Ground to Level 2
x | June 13, 2023 – Stripping formwork on the east side revealing parking access below grade
x | June 29, 2023 – Stripping of the roundabout leading to the Parking levels completed, Level 1 to 2
x | June 29, 2023 – Mechanical work started below grade, P Levels
x | June 29, 2023 – All conduit work for Pour 1 of Level 1 completed, awaiting concrete placement
x | July 7, 2023 – Current form of Parliament & Co. from Parliament Street showing verticals forms from Level 2 to Level 3 have started
x | July 7, 2023 – Final rebar for Level 2 has arrived, awaiting placement before the concrete pour
x | July 7, 2023 – Second pour for Level 2 started
x | July 14, 2023 – Conduit work is on-going for the last pour on the 2nd Level on the east side
x | July 14, 2023 – Verticals stripped on the south side from Level 2 to Level 3
x | July 14, 2023 – Mechanical work has started below grade
x | July 21, 2023 – Inside forms and rebar placement around the elevator core complete. Outer forms now being placed for concrete pour, from Level 2 to Level 3
x | July 21, 2023 – Southside perimeter column forms erected from Level 2 to Level 3
x | July 21, 2023 – Mechanical work continues, below grade
x | August 2, 2023 – First pour for Level 3 completed along the West Side
x | August 2, 2023 – Level 3 East Side floor decking and capital forming underway
x | August 2, 2023 – Main Level stripping of the concrete slab and reshoring
x | August 14, 2023 – Rebar and Conduit placement nearing completion on Level 3 East Side
x | August 14, 2023 – Forming Columns on Level 3
x | August 14, 2023 – Placing Forms for the North Perimeter Wall on Level 3
x | August 30, 2023 – Southwest view, showing Level 4 deck work extending north to Jessie’s Place
x | August 30, 2023 – View looking East, revealing the completed Level 3 above which deck forming has been completed on the South side
x | August 30, 2023 – South face of Parliament&Co reveals the structural columns and openings for future warehouse inspired windows
x | September 20, 2023 – South Elevation revealing the large expansive openings for the Warehouse inspired-windows
x | September 20, 2023 – North Elevation showing the garage entrance from Anna Hillard Lane
x | September 20, 2023 – West Elevation indicating the completion of the 4th level structural slab
x | September 26, 2023 – Back side of form in place and rebar erection has commenced for north perimeter wall
x | September 26, 2023 – Hanging pipe has now started on the main level
x | September 26, 2023 – 3/4 inch stone placed along the west side for future pedestrian sidewalk
x | September 27, 2023 – Rebar placement completed on the East Side, 5th Level Conduit work to begin
x | September 27, 2023 – Shotcrete on the North Perimeter Wall in progress, 5th Level
x | September 27, 2023 – View looking North revealing 5th Level decking progress
x | September 29, 2023 – Conduit work continues for the Northeast side
x | September 29, 2023 – Rebar placement and conduit work completed for the Southeast side, ready to receive concrete
x | September 29, 2023 – Shotcrete of the central northeast wall section completed, Level 3 to Level 4
x | October 11, 2023 – Guard rails installed in preparation of work to begin on above grade
x | October 11, 2023 – Piping installation continues below grade
x | October 11, 2023 – Block work started below grade
x | November 13, 2023 – Top and Bottom Rebar placement continues for 7th Level Slab
x | November 13, 2023 – Steel HSS work has started, fastened below the 2nd Level Slab
x | November 13, 2023 – Masonry block work continues on Level P1
x | December 6, 2023 – HSS work along the Eastside perimeter wall completed on Level 2
x | December 6, 2023 – Decking and placing bottom rebar continues for Level 8. Conduit works initiated.
x | December 6, 2023 – Duct work well underway below grade, along with hanging pipe for drains and erecting masonry block walls
x | January 30, 2024 – DensGlass on steel stud installation started on the sixth level, facing North and West
x | January 30, 2024 – Hoist installation complete on the North side entrance off Anna Hilliard Lane
x | January 30, 2024 – Steel stud erection on the perimeter of the 6th Level completed, image shown is facing south
x | March 8, 2024 – Densglass and Blueskin work on the perimeter has started
x | March 8, 2024 – Curtain wall window frames have started on the main level
x | March 8, 2024 – South facade revealing the progress with Densglass and Blueskin
x | March 18, 2024 – Densglass applied on the north side, 3rd level terrace section
x | March 18, 2024 – Riser connection work continues above grade
x | March 18, 2024 – Painting has started below grade
x | June 4, 2024 – Stripping of previously poured concrete columns, allows forms to be reused for the balance of verts from level 10 to 11
x | June 4, 2024 – Stripping of previously poured concrete columns, allows forms to be reused for the balance of verts from level 10 to 11
x | June 4, 2024 – Stripping of previously poured concrete columns, allows forms to be reused for the balance of verts from level 10 to 11
x | June 5, 2024 – Level 3 and 4 Curbs for the terraces facing West and North are completed.
x | June 5, 2024 – Level 3 and 4 Curbs for the terraces facing West and North are completed.
x | June 5, 2024 – Level 3 and 4 Curbs for the terraces facing West and North are completed.
x | June 15, 2024 – Construction continues
x | June 15, 2024 – Construction continues
x | June 15, 2024 – Construction continues
x | June 26, 2024 – Construction continues
x | June 26, 2024 – Construction continues
x | June 26, 2024 – Construction continues
x | July 31, 2024 – In preparation for pouring the Mechanical Penthouse Level
x | July 31, 2024 – In preparation for pouring the Mechanical Penthouse Level
x | July 31, 2024 – In preparation for pouring the Mechanical Penthouse Level
x | August 29, 2024 – Waterproofing on Level 4 started
x | August 29, 2024 – 11th Level Event Space View Facing West
x | August 29, 2024 – Window Installation facing West on Level 2
x | September 6, 2024 – Interior studwork for demising walls has started
x | September 6, 2024 – Insulation with vapour barrier added once the exterior windows are fully caulked
x | September 6, 2024 – Drywall added to the demising walls in preparation of acoustic ceiling placement